AVIXA CTS-I Certification Sample Questions

CTS-I Dumps, CTS-I PDF, CTS-I VCE, AVIXA Certified Technology Specialist - Installation VCE, AVIXA CTS-I - Installation PDFThe purpose of this Sample Question Set is to provide you with information about the AVIXA Certified Technology Specialist - Installation (CTS-I) exam. These sample questions will make you very familiar with both the type and the difficulty level of the questions on the CTS-I certification test. To get familiar with real exam environment, we suggest you try our Sample AVIXA CTS-I - Installation Certification Practice Exam. This sample practice exam gives you the feeling of reality and is a clue to the questions asked in the actual AVIXA Certified Technology Specialist - Installation (CTS-I) certification exam.

These sample questions are simple and basic questions that represent likeness to the real AVIXA Certified Technology Specialist - Installation exam questions. To assess your readiness and performance with real-time scenario based questions, we suggest you prepare with our Premium AVIXA CTS-I Certification Practice Exam. When you solve real time scenario based questions practically, you come across many difficulties that give you an opportunity to improve.

AVIXA CTS-I Sample Questions:

01. Two months after handover, an AV-over-IP system in a training suite becomes unusable. Every decoder stutters, and unrelated devices on the same access switch, including badge readers and room panels, start dropping off the network. The client's IT group replaced that access switch during a maintenance window, and multicast snooping is enabled on the new one. Traffic captures taken at the rack show the AV streams arriving on ports where no AV device is connected. The same encoders at the same stream settings ran correctly on the switch that was removed.
What is the most likely root cause?
a) The uplink to the core is saturated, so frames are being discarded from the media streams and from the other traffic sharing it.
b) The segment carries no querier, so snooping has no group membership to work from and every stream reaches all ports.
c) The media traffic is unmarked for priority, so it competes with control and building traffic inside the same queue on the switch.
d) The encoder bit rate is higher than the room needs, so the segment stays oversubscribed until each stream is set lower.
 
02. During a maintenance visit a technician notices that newer software is available for the codecs, displays and control processor in a working room.
What is the appropriate response?
a) Assess the change and schedule it, rather than updating during the visit.
b) Update every device, and record the versions before leaving, since current software is the maintained state.
c) Update only the control processor, since it coordinates the other devices.
d) Leave the software unchanged, since the room is currently working correctly.
 
03. While reviewing the issued documentation for a lecture hall fit-out, an installer compares two lines that cover the same material.
SCOPE OF WORK 3.4 — AV contractor shall install, terminate, label and test all AV cabling to the presentation wall. Conduit and backboxes on that wall to be installed by the electrical contractor.
BILL OF MATERIALS LINE 22 — Conduit, presentation wall drops — 14 ea.
What do the two lines together establish about the presentation wall conduit?
a) It is material supplied and installed by the electrical contractor, so the equipment list line is a duplicate that should be struck before ordering.
b) It is material supplied and installed by the AV contractor, so the scope line covers only the line-voltage portion of that wall's rough-in.
c) It is material supplied under the AV contract but installed by the electrical contractor, so delivery has to suit that trade's rough-in.
d) It is material listed in error, so the presentation wall drops are to be run as open cable supported from the structure above the ceiling.
 
04. Four entries were written up after a site survey of a training room.
1. Wall at display location: metal stud at 400 mm (16 in) centers, no blocking present.
2. Ceiling: gypsum board hard lid, two access panels in the corridor only.
3. Added floor box priced at the client's request; quotation issued to the general contractor.
4. Nearest dedicated receptacle for the rack: 3.5 m (11 ft) from the credenza.
Which entry belongs in the project's commercial record rather than in the technical site survey?
a) The stud spacing at the display location and the absence of blocking behind it
b) The quotation issued to the general contractor for the floor box added at the client's instruction
c) The hard-lid ceiling construction and the two access panels available in the corridor
d) The measured distance from the credenza to the nearest dedicated receptacle
 
05. Rough-in for a broadcast-style training room starts Monday. Reviewing the set, an installer finds that the signal flow diagram routes all four camera feeds through a video processor ahead of the switcher, and that no processor appears anywhere on the bill of materials. The rack elevation shows two spare rack units in the space where such a processor would sit.
What does this discrepancy most directly place at risk if it is left unresolved before the pull?
a) The rack's thermal load, since a processor drawing power continuously was never counted in the heat and airflow budget.
b) The control system's device list, since a processor added late will not appear in the programmer's port assignments.
c) The equipment delivery date, since a processor that was never ordered will not arrive alongside the rest of the head-end.
d) The cable count and pathway to the rack, since the camera runs terminate in different places under each document.
 
06. Loudspeaker substructure has to be hung from the structure above a two-story lobby, and the installer will work from a boom lift. The ceiling contractor is scheduled to set grid from rolling towers directly beneath the same bay on the same morning.
How should the installer handle the overlap?
a) Have the bay below the lift cleared for the duration of the overhead work and sequence the grid crew after it
b) Work the bay alongside the grid crew and keep hard hats and a tethered tool policy in force for both crews
c) Work the bay alongside the grid crew and post a spotter at the base of the lift to watch the towers below
d) Move the lift into the adjacent bay and reach across from there with nobody standing directly under the platform
 
07. After a second room is commissioned on the same segment, two endpoints in different rooms both become unreliable. Each responds sometimes and disappears at other times, and both were configured by hand from the same schedule.
What should be checked first?
a) Whether the network is congested by the traffic the second room added.
b) Whether the switch ports serving the two rooms are correctly configured.
c) Whether the two endpoints have been given the same address.
d) Whether the endpoints have lost their gateway configuration.
 
08. On a boardroom retrofit in an occupied building, the drawings mark a legacy loudspeaker cable bundle and a coaxial trunk in the ceiling as existing to be removed. Tracing the trunk, the crew finds it continues past the boardroom wall and into an adjacent training room that is in use today.
What is the crew's next step?
a) Cut the trunk at the boardroom wall and cap the far side, since only the boardroom portion is in the removal scope.
b) Confirm what the trunk still serves beyond the wall, since the removal scope cannot be settled until that is known.
c) Remove the loudspeaker cable now and leave the coaxial trunk in place, recording it as abandoned in the ceiling.
d) Disconnect the trunk at the head-end rack first, then cut it back to the boardroom wall and remove the slack.
 
09. At closeout the installer assembles the package that will be handed to the client and keeps its own project records separately. The two sets overlap in places, and the distinction decides what the client actually receives at handover.
Which of these is retained by the installer rather than delivered in the completion documentation?
a) The verification results recorded against the specified performance
b) The as-built drawing set for the installed system
c) The source programming files for the control processor
d) The crew's daily field reports for each day worked on site
 
10. Eighteen months after handover, a technician is sent to a lecture hall where one loudspeaker zone has gone silent. The as-built drawings show a junction above the corridor ceiling, and nothing is there. The crew that built the room had moved that junction during rough-in because the corridor was already full of mechanical services, and the move was documented at the time. The technician spends four extra hours finding the junction.
Which closeout documentation failure most directly produced that lost time?
a) The completion documentation was assembled without service manuals for the loudspeakers in that zone, so the technician arrived with no parts list, no terminal diagram and nothing to work the fault against.
b) The field modification was raised after the pathway had been moved rather than before the work, leaving the approval to catch up with a change already above the ceiling.
c) The drawing set was issued as an as-built without the rough-in redlines ever being incorporated into the sheets.
d) The punch list was closed out before the ceiling grid was reinstated over the relocated junction, so the concealed work passed out of view without a second look, and nothing above that ceiling was checked again.

Answers:

Question: 01
Answer: b
Question: 02
Answer: a
Question: 03
Answer: c
Question: 04
Answer: b
Question: 05
Answer: d
Question: 06
Answer: a
Question: 07
Answer: c
Question: 08
Answer: b
Question: 09
Answer: d
Question: 10
Answer: c

Note: For any error in AVIXA Certified Technology Specialist - Installation (CTS-I) certification exam sample questions, please update us by writing an email on feedback@edusum.com.

Rating: 4.8 / 5 (108 votes)